Determine the evidence and milestones for an orderly refinance.
An orderly refinance begins with the earliest decision that could force a change in plan, not merely with the loan’s maturity date. Work backward from funding, include time for evidence and conditions, and preserve enough time to pursue an alternative if proceeds or approval fall short. The schedule should expose uncertainty rather than compress every task into the final month.
The 2023 interagency CRE accommodation statement supports proactive engagement when payment difficulty is emerging. It does not establish a standard refinancing duration or guarantee an extension. The backward plan below uses hypothetical durations selected for one example.
Identify the actual payoff date and notice constraints
Assume a loan matures on day 180 from today. The borrower wants replacement funds available by day 165, preserving a 15-day operational margin. The current loan may have prepayment notice, release, hedge or extension provisions; the actual documents must determine those dates and costs.
Do not assume the current principal equals the final payoff. Obtain a preliminary obligation schedule early, then update with a formal payoff when appropriate. Include any known exit fee, prepayment premium, accrued interest and required release work in the proceeds model.
Work backward through accepted milestones
| Milestone | Hypothetical duration | Latest modeled completion |
|---|---|---|
| Funding and settlement readiness | 5 days | Day 165 |
| Final documents and closing conditions | 20 days | Day 160 |
| Final credit decision | 10 days | Day 140 |
| Reports and underwriting review | 35 days | Day 130 |
| Complete borrower package and lender selection | 20 days | Day 95 |
| Initial preparation begins | — | Day 75 |
The assumed sequence totals 90 days from day 75 to day 165. Some work may occur in parallel, while unresolved issues can add steps. The table is a dependency model, not a promised lender service level.
Starting on day 120 would leave only 60 days until maturity and 45 days until the desired funding date, short of this modeled 90-day path. That does not prove refinancing is impossible; it means the original plan no longer fits without an actually supported change.
Put a proceeds decision before the fallback window closes
Suppose a sale alternative would require 120 days from decision to cash, under a separately supported planning assumption. To receive sale cash by day 180, the latest modeled start is day 60, earlier than the refinance preparation start in the table. Waiting for a final refinance decision on day 140 would eliminate that particular fallback schedule.
The borrower therefore needs an earlier feasibility checkpoint, perhaps by day 45, to assess likely proceeds, available equity and material property issues. This checkpoint is a management choice based on the modeled lead times, not a contractual deadline.
A useful early question is whether the refinance can cover the payoff under a supportable downside. If the payoff is $5 million, modeled gross proceeds are $4.8 million and costs are 2%, net proceeds are $4.704 million, leaving $296,000 of required cash. If only $200,000 is available, the $96,000 gap needs a specific response before the fallback window closes.
Prepare the evidence that can change the answer
Start with current rent roll, operating history, debt documents, ownership structure, available sponsor cash and a list of property issues. Reconcile income definitions before comparing quotes. A rate discussion cannot resolve a missing lease, uninsured condition or unsupported cash-flow adjustment.
Identify upcoming events within the refinance horizon: lease expirations, tax or insurance changes, repair deadlines, capital calls and hedge expiry. A lender may evaluate conditions expected during its loan term even when today’s payment history is current.
Track each material item by owner, evidence date, requested action and lender response. A complete submission is one the lender can analyze, not merely a folder containing many files.
Separate an extension option from a contingency hope
If the existing documents contain an extension mechanism, identify notice timing, conditions, fee, required paydown and any hedge replacement. Determine what evidence is needed to establish eligibility. If extension requires discretion, label it proposed and obtain an actual decision.
Include the extension’s cash effects in the alternative model. A $100,000 paydown and $50,000 fee require $150,000 immediately even if the maturity moves. That may consume cash otherwise reserved for the eventual refinance gap. Do not count the same liquidity for both without a dated bridge.
Update the plan when evidence changes
Use a weekly or milestone-based review appropriate to the transaction. Record completed dates, revised durations and the amount of remaining float. If a report identifies follow-up work, add that work and the associated review instead of leaving the old funding date unchanged.
Confirm the final cash amount, payoff validity, signatures, insurance and funding authorization before treating the refinance as complete. A commitment can still contain conditions that prevent funding.
The finished schedule should show the earliest credible refinance date, the cash gap, the fallback decision window and the owner of every unresolved condition. Starting early is valuable because it preserves decisions that can still be executed, not simply because it creates a longer checklist.
Sources and evidence
- Federal Reserve — Prudent CRE Loan Accommodations and WorkoutsSection II Short-Term Loan Accommodations; Section IV Long-Term Loan Workout Arrangements; A Supervisory Assessment of Repayment Ability of Commercial Borrowers; B Supervisory Assessment of Guarantees and Sponsorships · Checked 2026-10-21 · Supervisory analysis of accommodations and workouts; examples and supervisory classifications are not borrower rights or guaranteed loan outcomes.
Source dates and applicability matter. Report an error or a changed source.