industrial credit evidence · Intermediate

Owner-user industrial relocation and double-occupancy costs

Build a monthly transition schedule for old rent, new property debt, moving costs and business disruption before financing an industrial relocation.

Illustrative examples. This is a constructed educational scenario, not a reported Jaken Finance Group transaction or financing offer.
The decision in brief

A lower stabilized occupancy cost can coexist with a cash deficit during the move. Test the overlap period and keep real-estate financing separate from unfunded working-capital needs.

An owner-user industrial relocation creates a temporary period when the business may pay for two locations while earning less than usual. Comparing the old monthly rent with the new mortgage payment misses that transition. The loan decision needs a dated operating cash schedule through move-in, commissioning and the end of the old lease.

Start with the business’s cash generation before occupancy costs, then add the actual obligations at each location. Identify what has already been deducted so the old rent is not subtracted twice. Include existing business debt and the new property debt separately, especially when the real estate and operating company are different legal entities.

Establish the operating handoff

Build a milestone schedule for building access, equipment delivery, utility capacity, fit-out, required approvals, test production and customer acceptance. Physical possession does not necessarily mean the business can operate at normal capacity. The relevant engineers, vendors and authorities should establish the conditions for the particular operation.

Map the old lease termination date and any restoration, notice or surrender obligations. Do not assume rent ends when equipment leaves. Likewise, a hoped-for subtenant or negotiated termination payment should remain a separate case until supported by the necessary agreements and consents.

A relocation budget also needs a funding classification. SBA’s 504 program page distinguishes eligible fixed-asset uses from working capital and inventory, which it lists as ineligible uses. That product-level distinction matters when evaluating a possible structure, but it does not decide the eligibility of every line in a specific project. Ask the lender and CDC to classify actual costs under current controlling requirements.

Worked exhibit: the third month determines opening cash

Assume a hypothetical business generates $80,000 monthly before occupancy costs and debt service under normal operations. Old rent of $20,000 continues through month 4. New property debt service of $30,000 and new owner operating costs of $10,000 begin in month 1. Existing business debt service is $10,000 monthly.

The move costs $70,000 in month 3. Operational interruption reduces pre-occupancy business cash by $25,000 in month 3 and $10,000 in month 4. Those amounts are lost cash contribution after the associated variable costs, not lost gross sales. No deposit refunds, tax distributions or new working-capital borrowing are assumed.

Month Business cash after disruption, before occupancy/debt Old rent New property debt and costs Business debt Move cash Net change
1 $80,000 $20,000 $40,000 $10,000 $0 $10,000
2 $80,000 $20,000 $40,000 $10,000 $0 $10,000
3 $55,000 $20,000 $40,000 $10,000 $70,000 −$85,000
4 $70,000 $20,000 $40,000 $10,000 $0 $0
5 $80,000 $0 $40,000 $10,000 $0 $30,000
6 $80,000 $0 $40,000 $10,000 $0 $30,000

Starting with zero unrestricted cash, cumulative cash reaches $20,000 after month 2, falls to −$65,000 after month 3, remains there in month 4 and ends month 6 at −$5,000. The minimum opening cash needed to avoid a negative balance is therefore $65,000. If management also requires a $30,000 minimum operating balance, opening unrestricted cash must be $95,000 under this scenario.

The business eventually produces $30,000 monthly after the modeled obligations. That steady-state result does not eliminate the earlier funding need. A lender considering annual coverage should also see the monthly trough.

Stress the delay at the right location

Suppose commissioning is delayed two months after the original move date. Identify which costs extend: old rent, temporary utilities, storage, duplicate staffing or equipment rental. Determine whether business interruption repeats or changes. A blanket two-month increase in interest can omit the larger operating effect.

For a narrow sensitivity, assume only two extra months of old rent are required after month 4, with every other base-case assumption unchanged. Additional cash use is $40,000, and six-month ending cash falls from −$5,000 to −$45,000 before opening reserves. The lowest point remains −$65,000 in this particular timing because the later months still add $10,000 each. A delay can reduce final cash without changing the earliest peak need; the dated schedule reveals that distinction.

A different delay that postpones production recovery would deepen the trough. Keep the mechanisms separate so the team knows whether accelerating permits, negotiating old rent or arranging working capital would actually solve the problem.

Reconcile entity transfers and financing availability

If the operating company pays rent to an affiliated property company, show the transfer in each entity and eliminate it in a combined view. The combined cash model should include actual mortgage debt, property expenses and business debt once. Legal restrictions or guaranty scope may still limit which cash is available to each creditor.

Distinguish committed working capital from a possible line of credit. A line may have borrowing-base conditions, covenants or unused-capacity limits. Include its interest and repayment if drawn. Do not insert a line as permanent equity while omitting its debt service.

For purchase financing, show acquisition equity separately from the $95,000 operating reserve in the example. Using all available cash for the down payment can leave a technically financed building with an unfunded move.

Give the lender an executable transition case

Submit the milestone schedule, old lease obligations, vendor payment dates, disruption assumptions and evidence of available liquidity. Ask which costs are eligible for the proposed facility and which require a separate source. Record the conditions for each disbursement and the date funds can actually be used.

The relocation decision is ready when the business can fund both locations, complete the move and maintain operations through a credible delay. A favorable stabilized payment comparison is useful, but it should come after the cash path to that stabilized operation is demonstrated.

Sources and evidence

  1. SBA — 504 loansHow do I use a 504 loan? Eligible uses and exclusions · Checked 2026-10-21 · Source-specific context; numerical examples and decision workflow are original hypothetical analysis.

Source dates and applicability matter. Report an error or a changed source.

Keep working through the decision

Related resources